A Shortened Statute Of Limitation - How Low Can You Go?

Written By: Randy J. Heller

08/01/18
In construction contracts, it is fairly common to have a provision shortening the time within which to bring suit for any claims arising out of the contract. A New York statute provides that you may take as long as 6 years to bring a claim for breach of contract, but allows the parties to agree to a shorter time in their contracts. Are there any limits?


Case law is replete with examples of shortened periods of limitation: one year is common; 6 months is allowed; even 90 days has been upheld as a reasonable period of limitations on certain municipal contracts.

In a recent case, a contractor included a provision in its subcontract shortening the period of limitations to “one year from substantial completion.” The subcontractor achieved substantial completion in 2012 and started an action for its contract balance in 2016. The contractor moved to dismiss the case as having been commenced after the period of limitations expired. It lost!

Here’s the rub: The subcontract also provided that the subcontractor’s right to payment didn’t accrue until the contractor received payment from the owner, the NYC School Construction Authority. Because the SCA did not evaluate change orders and credits, or make payment to the contractor, until 2014, the period of limitations to sue for its money would have expired even before the subcontractor was entitled to the money. In other words, the limitation period in the subcontract conflicted with the payment provision, acting to nullify any claim the subcontractor might have had. Under those circumstances, the court held the one-year limitation period to be unenforceable.

The court reiterated that “there is nothing inherently unreasonable about the one-year limitation period to which the parties freely agreed.” But the problem wasn’t with the duration, the problem was with the accrual date, i.e., when the clock started ticking. Because the circumstances would have had the limitations period run out before the claim could be brought, it was held to be unenforceable.

The takeaway? Shorten the limitations period all you want. Just be sure that there is no other impediment to letting the clock start ticking on the bringing of the claim.
 


 
 
about the authors

Randy J. Heller

Partner

For over forty years, Mr. Heller has specialized in construction law and litigation, representing some of the largest and most successful contractors in the nation.

View Profile